Dear Residents,

Please see below Amenity/Construction Update;

  • New pool construction is complete and is scheduled to be inspected by the Health Department.
  • Both manhole projects have been completed and sod is to be reinstalled over dig site.
  • Landscaping Irrigation is currently being reconnected and tested.
  • New swing set is installed with fall zone material and barrier still to be installed.
  • New stall dividers to be installed in existing Amenity restrooms.
  • County to install water meter to new Pavilion restrooms which will allow a final plumbing inspection to be conducted.
  • Once final plumbing inspection and Health Department Pool inspections are passed, the final building inspections will be conducted.

We appreciate your patience and are working to complete this project soon.

Adobe Acrobat Reader

This site provides information in PDF format. For your convenience, we have provided a link below to get the free Adobe Acrobat Reader.

Get Adobe Acrobat Reader

This site provides information using PDF, visit this link to download the Adobe Acrobat Reader DC software.